This release was issued under a previous government.

The Shaftesbury Ferry near Peace River will open approximately one month late due to refurbishing while the Crowfoot Ferry, south of the Trans-Canada Highway near Bassano, will be closed for the season due to flood damage.

Shaftesbury Ferry

The Ferry operates on the Peace River about 60 km south of the Town of Peace River along Hwy 740. It is used by light local traffic and farmers hauling equipment. It was originally designed in 1962.

Retrofits and refurbishments to Shaftesbury Ferry

  • Significant upgrades required to ensure reliable and safe operation and extended life of the ferry.
  • Current propulsion system for the tug has reached its service life and needs a new engine, gear box and fuel tanks.
  • Protective fire coatings need to be removed and a new fire retardant material coating needs to be applied prior to the installation of the new engine, gear box and fuel tanks.  A fire suppression system will also be installed in the tug engine room to meet Transport Canada regulations.
  • Sand blasting and painting required on exterior of the ferry.
  • Retrofits anticipated to be completed late May 2014.

Crowfoot Ferry

The Ferry crosses the Bow River along Range Road 201, about five kilometers south of the Highway 1-Highway 56 junction. The launch area sustained significant damage because of the 2013 flood and it is not anticipated that the ferry will be able to open for the 2014 season. The work required is unique and includes significant instream activity to re-establish more than 325 metres of bank, along with the launch pads.

2013 Flood Damage to Crowfoot Ferry:

  • Last year’s flood caused little damage to the ferry – a few gouges in the hull that were assessed as minor.
  • Damage to both landings was extensive.
  • East bank: the anchor line tower collapsed, the landing was buried by one metre of silt and rock accumulation, and piles on the east guideline tower were exposed.
  • West bank: the crew quarters trailer washed away, the ferry house was completely flooded, electrical and propane lines were severed, and the shore water supply was contaminated. A caterpillar used to secure the ferry was also submerged and written off due to water damage.
  • Total repairs for the crossing, shore facilities and vessel are estimated to cost $1.255 million.

All other ferries operated by Alberta Transportation will open once the rivers are free of ice. This is typically late April to early May, but dependent on local conditions.